Anne Soojus AS
Construction of District Cooling station, 2016

Valmet Technologies OY
Construction of Skövde CHP (SWEDEN), 2016
Installation of pipelines and equipments; stainless steel pipelines upto 2,5 km ; carbon steel pipelines upto 2,5 km

Valmet Technologies OY (2)
Oskarshamn BR-5 power station construction (SWEDEN), 2015
Installation of low pressure piping and different equipment

VKG AS
Oilplant Petroter II-III connection pipelines, 2014
Erection of 14 km length pipelines weighing 600t, 380t of steel structure, 104000 manhours of work

Wärtsilä Finland OY
Kiisa ERPP construction, 2013
Pipelines and gas duct erection and installation of various equipment

Eesti Energia Tehnoloogitööstus AS
Construction of Enefit 280 Oilplant in Narva, 2012
Waste heat boiler installation 594 t
Boiler and system piping 582 t and equipment installation

MW Power OY
Constriction of Lahti Energia Kyvo CHP (FINLAND), 2011
Installation on process pipelines and equipments

MW Power OY (2)
Vattenfall AB (SWEDEN) Jordbro CHP construction, 2010
Installation of high & low pressure pipeline, installation of various equipment

Municipality of Gotland
Renovation of fuel terminal in Visby (SWEDEN) port, 2010
Installation of Jet A-1, diesel and petrol pipelines

Fortum Termest AS
Construction of Pärnu Fortum CHP, 2010
Installation of high & low pressure pipeline(1.5Km), installation of various equipment

Reval Shipbuilding OÜ
Renovation of fuel tanker Brovig Fjord, 2009

Noviter OY
Enlargement of Helsingi Energia boiler house (FINLAND), 2008
Installation of pipes and equipment

Paide Vesi AS
Renovation of Water Treatment Plant, 2008
Installation of Stainless steel pipelines and equipments

Noviter OY (2)
Construction of Väo CHP, 2009
Installation of high & low pressure pipeline, installation of various equipment

Fortum Tartu AS
Enlargement of Tartu CHP, 2009
Construction of high & low pressure pipeline(2.5Km), installation of various equipment

SRC Marine and offshore
Renovation of fuel tanker Vedrey Fram, 2007
Installation of stainless steel pipelines, total 3 km

SRC Marine and offshore (2)
Construction of chemical tanker Vedrey Tora, 2006
Installation of stainless steel pipelines

Nybit AS
Expansion of Nynas Bitumen terminal in Muuga Port, 2006
Construction of bitumen tank 7000m3 and erection of bitumen tanks 2 x 50m3
Construction of railway loading platform and steel structures installation, erection of pipeline & equipment

FKSM AS / Noviter OY
Balti Power Plant, 2004
Installation of pipelines, Construction of pump house & railway loading platform

Galvex Estonia OÜ
Muuga Port, 2004
Installation of pipes; material grade EN 1.4307 & 1.4432; size DN15 - DN250; 5 km